› Denny’s Brings Canada’s Modern Diner to Woodstock This October› From Vehicle to Mobile Power Station: KAIYI X7 Hybrid Unlocks New Possibilities for Outdoor Power› Cygnus Announces Scheme becomes Effective› EXIT-CVD research consortium launches clinical studies to transform cardiovascular care across Europe› Meet the other 10 candidates running for election as Ottawa's mayor› John Ivison: Russia’s deadly crosshairs could be aiming at the heads of Canada’s defence contractors› Welcome Hill visitors, yes, but at that cost? | Letters to the Editor› Government planning 'hyperscale' $1.5B data centre for National Capital Region› Director Alex Gibney on terrifying Musk documentary: 'It's not a funeral; it's a warning'› How high inflation is hurting Trump's Republicans in U.S. midterm campaign› Denny’s Brings Canada’s Modern Diner to Woodstock This October› From Vehicle to Mobile Power Station: KAIYI X7 Hybrid Unlocks New Possibilities for Outdoor Power› Cygnus Announces Scheme becomes Effective› EXIT-CVD research consortium launches clinical studies to transform cardiovascular care across Europe› Meet the other 10 candidates running for election as Ottawa's mayor› John Ivison: Russia’s deadly crosshairs could be aiming at the heads of Canada’s defence contractors› Welcome Hill visitors, yes, but at that cost? | Letters to the Editor› Government planning 'hyperscale' $1.5B data centre for National Capital Region› Director Alex Gibney on terrifying Musk documentary: 'It's not a funeral; it's a warning'› How high inflation is hurting Trump's Republicans in U.S. midterm campaign
Latest

Re-occupancy of Bridgeland Place affordable housing high-rise pushed to late 2028

Calgary Herald ·

Work is getting underway this week on a $90-million project to refurbish Bridgeland Place — an affordable housing high-rise located across the Bow River from downtown Calgary.

While the project’s completion date has been extended from what was originally expected, the building will ultimately help address the affordable housing situation in the city by adding 203 units into the market.

“In order for us to maintain an acceptable level of service for our residents, the building needed to be upgraded at a pretty substantial amount,” said Bo Jiang, Calgary Housing’s interim chief executive.

Your weekday lunchtime roundup of curated links, news highlights, analysis and features.

A welcome email is on its way. If you don't see it, please check your junk folder.

“(Gutting it) provided the best opportunity for us to do it right, so we were able to clean out any hazardous materials that might have been still in the building, as well as make sure of the structural integrity of the core structure.”

Redevelopment of the city-owned asset, which was originally built in 1971 on the north side of Memorial Drive, is under the management of Calgary Housing, a wholly owned subsidiary.

The tower previously included 210 rentals, providing low-income Calgarians with subsidized, below-market housing for more than 50 years. It was decommissioned and vacated in 2023, after Bridgeland Place was deemed to be past its serviceable life and issues were cited with its water and ventilation systems.

After its final tenants were moved out and relocated, the tower’s interior was stripped down to the concrete in 2024, in preparation of installing new electrical, water, heating and ventilation systems and plumbing.

Last winter, Calgary Housing submitted a development permit to the city to refurbish the tower’s amenities and to upgrade the original exterior cladding with a more energy-efficient building envelope.

Redevelopment of the exterior envelope will begin this week, to make it more weather-resistant and energy-efficient. To that end, cladding and windows will be replaced and balconies will be removed.

But with strong bones and its structural integrity intact, the tower has been spared from demolition, Jiang said, adding inspections earlier this decade revealed Bridgeland Place’s concrete was still in good condition.

“So the decision that we made to keep it was validated once more, and we continue to go down the path of just renewing the building rather than demolishing and rebuilding,” he said.

The timeline for the overhaul is two years and Jiang said new tenants should be moving into the tower by late 2028 or early 2029.